News

Cop28: Indonesia, ADB, owners agree to shut coal-fired power station early under climate change plan

[ad_1]

Indonesia and the Asian Development Bank have agreed a provisional deal with the owners of the Cirebon-1 coal-fired power plant to shut it down almost seven years earlier than planned, the ADB’s senior climate change energy specialist said.

The deal, announced during the Cop28 climate talks in Dubai on Sunday, is the first under the ADB’s Energy Transition Mechanism (ETM) program, which aims to help countries cut their climate-damaging carbon emissions.

Cop28: what stance will China take on coal, renewable energy commitments?

Supporting a US$20 billion (HK$156 billion) Just Energy Transition Partnership agreed last year that aims to bring forward the sector’s peak emissions date to 2030, the ADB hopes to replicate it across other countries in the region.

“If we don’t address these coal plants, we’re not going to meet our climate goals,” David Elzinga, the ADB’s Principal Energy Specialist, said on the sidelines of the conference.

“By doing this pilot transaction, we are learning what it takes to make this happen,” Elzinga said. “We’re very much shaping this as something we want to take to other countries.”

02:31

Indonesia opens largest floating solar power plant in Southeast Asia as part of green push

Indonesia opens largest floating solar power plant in Southeast Asia as part of green push

ADB also has active ETM programmes in Kazakhstan, Pakistan, the Philippines and Vietnam, and is considering transactions in two other countries, it said.

Under the non-binding framework deal, signed by ADB, Indonesian state-owned power utility company PT PLN, independent power producer PT Cirebon Electric Power (CEP) and the Indonesia Investment Authority, a power purchase agreement for the 660 megawatt plant – a key supplier to the capital Jakarta – will be ended in December 2035 instead of a planned date of July 2042.

Can Cop28’s plan to triple renewable energy finally edge out fossil fuels?

As it opened only in 2012, the plant, operated by CEP, could have been expected to run for 40 or more years, so retiring it in 2035 would avoid over 15 years of greenhouse gas emissions from the site, the ADB said.

The deal is subject to due diligence, including assessing its impact on the environment, the company’s workers and society more broadly, and the broader electricity system, but is expected to close in the first half of 2024.

[ad_2]

Source link

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button